Proof of delivery process: from delivery to invoice, with missing POD chasing

Updated 19 October 2026 · Written by Paul, founder of Steplane, a logistics process specialist with over 13 years in logistics, including at some of the biggest freight forwarders in the world.

In short: A proof of delivery process gets a valid, signed POD into the job file soon after every delivery, so the invoice can go out the same day. A valid POD shows who received the goods, where and when, how many packages, and their condition, with any remarks. Missing PODs are chased from the first working day.

Many late invoices in road freight are not billing problems. They are POD problems: the signed CMR or delivery receipt is still in the cab, in a carrier's inbox or on a driver's phone. The step table below fixes that with one owner, one trigger and one record per step.

Covers EU and UK road freight under CMR and US freight under the bill of lading. General information, not legal advice.

Key facts

What a valid POD contains

ItemEU and UK road (CMR)US (bill of lading or delivery receipt)Why it matters
Shipment referenceCMR number and your job numberBOL or PRO number and your load numberLinks the POD to the right invoice
Receiver's name and signatureBox 24 signed, with a printed nameSignature and printed nameShows who took the goods
Company stampConsignee's stamp in box 24Often not used; printed name and title insteadShows the goods reached the right company
Date and timeDate, plus arrival and departure timesDate and time, plus in and out timesStarts claim deadlines and proves waiting time
QuantityPackages received vs packages on the notePieces received vs pieces on the BOLShortages must be noted here
Condition and remarksReservations for visible loss or damageExceptions: damaged, short, refusedA clean POD makes a later claim much harder
Seal numberIf sealed: seal intact, number matchesIf sealed: seal intact, number matchesSeparates transit loss from loading errors
Legible copyFull page, all boxes readableFull page, all fields readableCustomers reject cut-off or blurred photos

An electronic POD (e-CMR, app signature, photo with GPS and time) works if your contract with the customer and the carrier accepts it. Write that into the transport order and the customer terms.

The POD process: step, owner, trigger and record

#StepOwnerTriggerRecord
1Put the POD rule in the transport order: POD within [24] hours, payment terms start on receipt of POD and invoiceOperationsBooking the carrierTransport order
2Brief the driver: signature, printed name, stamp, times, count, remarksCarrier or own fleet managerDispatchDriver instructions
3Get the signature and remarks at deliveryDriverUnloading doneSigned CMR, BOL or e-POD
4Send a photo or scan of the full PODDriver or carrierSame day as deliveryPhoto or scan in the job file
5Check the POD: legible, signed, dated, count matches, remarks readOperationsPOD receivedJob status "POD OK" or "POD with remarks"
6If there are remarks, open a claim file and send any notice in timeClaims ownerPOD with remarksClaims log entry
7Log waiting time and extras shown on the PODOperationsPOD checkedExtras log
8Hand the job to billing with the POD and extrasOperationsStatus "POD OK"Billing hand-off
9Invoice with the POD attachedBillingHand-off receivedInvoice and POD sent
10Chase any POD still missingOperationsDelivered, no POD after 1 working dayMissing POD list
11File the original and the scanOfficeInvoice sentArchive by job number

Chasing missing PODs

Keep one list: every job delivered but without a checked POD. Review it every morning. A simple chasing plan:

WhenActionTo
Day of deliveryAsk for a photo of the signed POD before the driver leaves the areaDriver or carrier dispatch
1 working dayReminder by email or message, with the job numberCarrier
3 working daysPhone the carrier; ask the consignee for its copy at the same timeCarrier and consignee
5 working daysHold the carrier's payment under the transport order terms; escalate to the managerCarrier, your manager
10 working daysInvoice with other proof (tracking, consignee email) if your customer accepts itYour customer

These intervals are a starting point. Set your own, and agree them with your carriers in writing. Holding a carrier's payment only works if the transport order says so.

Remarks on the POD and claims: EU and US

TopicEU and UK (CMR)US (Carmack)
Visible damage or shortageReservation at delivery, giving a general idea of the loss or damage (art. 30(1))Write the exception on the delivery receipt before signing
Hidden damageWritten notice within 7 days, Sundays and public holidays excluded (art. 30(1))Report as concealed damage as soon as found and request an inspection
DelayWritten reservation within 21 days (art. 30(3))Claim within the bill of lading time limit
Filing the claimCourt action within 1 year; a written claim suspends the period (art. 32)At least 9 months to file; at least 2 years to sue from written disallowance (49 U.S.C. 14706(e))
Carrier's answerNo fixed periodAcknowledge within 30 days; decide within 120 days (49 CFR 370.5, 370.9)

The POD is the first document a claims handler asks for. Keep the original with the remarks; a photo cut off at the bottom often loses the one line that matters.

Scanning and storing PODs

How POD speed changes when you get paid

Example: a load is delivered on 3 March. Your payment terms are 30 days from invoice.

POD same dayPOD after 8 days
POD in the file3 March11 March
Invoice sent3 March11 March
Payment due2 April10 April

Eight days late on every load means eight more days of your money with the customer, while you have already paid the carrier or the driver. Measure it as POD return time and days from delivery to invoice.

Get the booking and carrier kit

Nine steps from the customer's order to the job handed to billing: a transport order (rate confirmation in the US version) with POD and payment terms, a booking checklist, a carrier register with a margin check, and a POD and billing hand-off. EU and US versions in Word and Excel.

Get the booking and carrier kit

€49 (about $55) per kit, one-time. EU and US versions. Any 3 kits €99, all 6 kits €199. 14-day money-back guarantee.

Related guides

Sources

Questions

What is a proof of delivery?

The signed document or electronic record showing who received the goods, where and when, how many packages and in what condition. In European road freight it is usually the signed CMR note; in the US, the signed bill of lading or delivery receipt.

What makes a POD valid?

A readable signature with a printed name, the date and ideally the time, the company stamp where used, the quantity received and any remarks on damage or shortage. It must be linked to the shipment by its reference.

What should I do when a POD is missing?

Chase the carrier from the first working day, ask the consignee for its copy at the same time and, if your transport order allows, hold the carrier's payment until the POD arrives.

Can a customer refuse to pay without a POD?

Many customer contracts require a POD with the invoice. Under the RHA Conditions of Carriage 2026, a UK haulier's customer cannot withhold payment for a missing POD unless it reported non-delivery within 48 hours (cl. 9(3)). Check your own terms.

Does a remark on the POD count as a claim?

No. Under CMR it is a reservation that protects your rights. The claim with an amount comes later, and court action must start within 1 year unless a written claim suspends the period.

How long should I keep PODs?

At least until the claim periods have passed: 1 year after delivery under CMR, 3 years for wilful misconduct. US motor carriers keep records of freight delivered for 1 year under 49 CFR 379. Tax rules may require longer.

Is a photo of the POD enough?

Often yes for invoicing, if the customer accepts it and the photo shows the whole page clearly. Keep the original for claims.